28 Apr

NZ Transport Agency planning for restart of billions-worth of roading projects

Joel Maxwell05:00, Apr 21 2020

Planning is underway to restart significant roading projects such as Transmission Gully, untouched since lockdown.

However questions remain about whether there are even enough staff left in New Zealand to complete them – or when they might now be finished.

Last week the Government released a broad-stroke outline of what could happen when the nation steps down to Level 3 restrictions: allowing construction work with health, safety and distancing controls.

NZ Transport Agency senior manager Andrew Thackwray said on Friday staff were developing plans for restarting work nationwide on its highway project sites.

The Gully route cuts through the hills beside the existing State Highway 1. FILE
SUPPLIEDThe Gully route cuts through the hills beside the existing State Highway 1. FILE

Billions-worth of highway projects around New Zealand  – including the long sought-after Transmission Gully – were shut down during Level 4.

Thackwray said the planning, in tandem with the Government, covered how work would restart during different alert levels, while following coronavirus restrictions and protections for workers and road users. 

It was too early to say when work might resume on specific capital projects or non-essential highway maintenance activity he said, speaking before the Government announced Level 4 would end on April 27.

The agency did not answer questions on whether sufficient staff were even available to work on Transmission Gully once it was allowed to restart. It could not say what effect the delay would have on planned penalties, including a $10m penalty if the road was not opened by December 18.

Works stopped on Transmission Gully at the start of the level 4 lockdown. FILE
ROSS GIBLINWorks stopped on Transmission Gully at the start of the level 4 lockdown. FILE

As previously reported by Stuff, a Transmission Gully contractor, who did not wish to be named, said work was likely to be delayed even before lockdown because staff were leaving “in droves”. Many Australian staff due to return from their days off decided to quit rather than be stuck in New Zealand. 

Thackwray said the Level 4 shutdown “and other effects of Covid-19” would likely have an impact on the completion dates for many projects.

“But it is too early to say what the impact may be for individual projects.”

About $1.3b worth of roading work was underway on State Highway 1 in the Wellington region – split between the billion-dollar Transmission Gully project and the northern section of the Kāpiti expressway.

Transmission Gully roading works at Pauatahanui. FILE
ROSS GIBLIN/STUFFTransmission Gully roading works at Pauatahanui. FILE

The Peka Peka to Ōtaki section of the expressway was initially expected to open this year but is now planned to open early next year. 

Transmission Gully, planned in one form or another for about a century, was initially expected to open this month – then, pre-coronavirus, was planned to open by November.

After this date late penalties would kick in for the contracted builder, including a $10m penalty if the road is not opened by December 18.

Construction began in 2015 on the 27 kilometre-long road, connecting Linden in north Wellington to just north of Paekākāriki on the Kāpiti Coast​.

Once both sections are opened there will be four lanes running continuously from north of Ōtaki to the Terrace Tunnel, in central Wellington.

The $650m first section of the Kāpiti expressway opened in 2017.

Leave Your Reply

Your email address will not be published.

*