The Western Belfast Bypass, a four-lane, 5-kilometre stretch of highway north of the city, was 80 per cent completed, the NZ Transport Agency (NZTA) said.
“Over 375,000 hours have been worked on this project so far and it is progressing well as this drone footage shows,” Christchurch highways manager Colin Knaggs said.
The $122 million Western Belfast Bypass project is set to be completed in early 2018. NZTA says it is now 80 per cent complete.
“Aside from some road marking and other minor finishing touches, this section of the project is also close to being finished.”
The Dickeys Rd bridge under construction, as part of the Western Belfast Bypass programme.
“Before the project team could start building they had to carry out ground improvement work, constructing around 2400 columns of gravel and stone into the ground to make it denser,” he said.
“This reduces the effects of liquefaction and ensures the bridge embankments remain stable, preventing damage to the bridge structures during an earthquake.”
A further 30 steel-cased concrete piles, up to 20 metres deep, support each structure.
Once completed, in early 2018, NZTA forecast 24000 cars will use the bypass every day.
– Stuff
Thank you for this post! I really enjoyed how you broke down “Western Belfast Bypass
progress – Cubic Transport Services” — it’s not every day you
read such a practical explanation. These days I’m digging into similar subjects as well, and I keep some notes here: xush kelibsiz bonus Keep it up!
Thanks for putting this together! I honestly enjoyed how you explained “Western Belfast Bypass
progress – Cubic Transport Services” — it’s not every day you read such a clear write-up.
These days I’m digging into this topic myself, so
I started some notes over here: Starzbet TR Great work!